The London 2012 Organizing Committee (LOCOG) has released new aerial images showing the transformation of the Olympic Park as 2012 approaches.

The latest aerial shots show the Olympic Park ‘big build’ now over 90% complete, with the Olympic Delivery Authority (ODA) on track to hand the site in London over to LOCOG early next year.

LOCOG chair Seb Coe said: “A huge amount has been achieved over the past 12 months with iconic new venues completed and test events bringing world-class sport to the Olympic Park for the first time. We still have much to do but there is growing excitement as we count down to the Games next summer.”